On January 22, 2025, Joint-Stock Company BAO concluded an agreement with the Central Finance and Contracts Agency for the implementation of project No. 2.2.2.1/1/24/A/006 “Establishment of waste processing facilities”.
The overall objective of the project is to establish a construction waste processing facility intended for the processing of construction waste into secondary raw materials, thereby facilitating the transition to a circular economy, as well as to take measures to promote public education and environmental awareness.
The total eligible costs of the project are EUR 1,051,280, of which it is planned to receive co-financing from the Cohesion Fund in the amount of EUR 606,680.00.
On May 5, 2025, an agreement was concluded with GmbH “Prall-Tec” for the supply of a construction waste processing facility.
The project is scheduled to be implemented by December 21, 2025.